This glossary, containing over 400 keyword definitions that relate Microsoft Project and Project Management, is an excerpt from Project Companion—a free download from Project Learning Limited.
Accrual method | Costs for work and fixed costs against tasks in Microsoft Project can vary how they are accrued against time. For example, $1,000 for a 10 day task could be accrued at:
| ||||||
Actual Bars | Bars on a Gantt chart drawn from the actual start to complete through for tasks in progress and to actual finish for those that have been completed. | ||||||
Actual Cost (Assignment) | Costs incurred for work already performed by a resource on a task. This value can be calculated by Microsoft Project or entered by the user. | ||||||
Actual Cost (Resource) | For all assigned tasks, this value shows the sum of costs incurred for the work already performed by a resource. | ||||||
Actual Cost (Task) | Costs for work already performed by all resources on a task, plus any other actual costs for the task. This value can be calculated by Microsoft Project or entered by the user. | ||||||
Actual Duration | Until the project is progressed, this value is 0. If an Actual Start and Actual Finish are present for the task, this value will be the duration between them. If no actual finish is present, it is a value entered by the user, or calculated around the task's percent complete. | ||||||
Actual Start | The date (and optionally time) that the task or assignment commenced. Can be entered (over the default of NA) or calculated from an entered actual finish or an entered percent complete value. | ||||||
Actual Finish | The date (and optionally time) that the task or assignment was completed. Can be entered (over the default of NA) or calculated from an entered percent complete value of 100%. | ||||||
Actual Work (Assignment) | Until the project is tracked with actuals, this value is 0. When actual work information for tasks or assignments is added, this value will increase. It will also increase, relative to the task's percent complete value if the updating task status updates resource status option is selected. | ||||||
Actual Work (Resource) | The amount of work that has already been done against the assignments for a resource. It is a calculated value. | ||||||
Actual Work (Task) | The amount of work that has already been done against a task. This value can be calculated by Microsoft Project or entered by the user. | ||||||
ACWP | Within earned value analysis, the Actual Cost of Work Performed. This field shows actual costs incurred for work and any fixed costs for tasks, up to the project status date or its current date. When compared to BCWP, cost variance values (CV) can be determined. | ||||||
Aggregation | The summing up of resource demands over time. If a resource is scheduled to work on two tasks simultaneously, aggregation will add up the units assigned to the tasks per time unit and display the total units assigned - in this case two (or 200%). If this number exceeds the resource's max units, then a resource conflict may ensue. | ||||||
ALAP | Tasks will be scheduled to finish on their late finish date rather than their early finish date (as with ASAP). This can be set on a task-by-task basis and it is the default setting when projects are scheduled from a finish date (established within the Project Information dialog box). | ||||||
Analysis Toolbar | Provides shortcuts to additional analysis functions and modules. | ||||||
ASAP | By default, tasks are scheduled to commence as soon as they possibly can. This is either on the project start date or as soon as their predecessors have been completed. This can be set on a task-by-task basis and it is the default setting when projects are scheduled from a start date (established within the Project Information dialog box). | ||||||
Assign Resources Dialog | A dialog box to quickly create assignments. Invoked by the Assign Resources button. Only shows assigned units values and not assigned work. Can be used for assignment drag and drop. For more sophisticated assignments, use the task entry view. | ||||||
Assigned Units | The rate at which the resource will perform an assignment. Usually at a flat rate (100% being the default), units can be varied with a contoured assignment. Units assigned should not exceed the max units of resource availability. Assigned units is a variable within the scheduling formula. | ||||||
Assigned Work | Work (and hence time) assigned to calculate the duration of an assignment. Part of the scheduling formula, it is calculated as the total work for the assignment less any overtime work. If only one resource is assigned to a task, the assigned work and the total work are the same. | ||||||
Assignment Delay | To make an assignment commence later than the scheduled start of a task (or any other assignments against that task), an assignment delay can be manually applied. Assignment delays can not be cleared by resource leveling. | ||||||
Assignment Finish | The date (and time) at which assigned work will be completed by. | ||||||
Assignment Start | The date (and time) at which an assignment can commence. Calculated as the task's (that the assignment is against) scheduled start plus any assignment delay or leveling delay values. | ||||||
Assignment Drag and Drop | A method to quickly create assignments by dragging a resource from the assign resources dialog to a task on a row of a table by using the Assign Resource cursor. Multiple assignments will use the Assign Multiple Resources cursor. | ||||||
Assignment Replacement | The process where an assignment for one resource is swapped with another resource. When this is accomplished, check that the assigned work and assigned units values are appropriate to the new assignment. | ||||||
Assignments | An assignment is the relationship between a task and a resource to perform the task. This assignment creates measurable work - one of the three project resources. | ||||||
AutoFilter | AutoFilters are a quick and easy way to select relevant information within one of Microsoft Project's tables. They are turned on and turned off with AutoFilter button on the formatting toolbar. Available to each field within the table, they provide selections based upon the field's values as depicted in the table. Global Filters can be created by saving AutoFilter criteria. | ||||||
Autolink | If tasks are cut or copied, their links may be re-established when pasted if the Autolink option is selected. This also affects when tasks are dragged and dropped or inserted within a sequence of already-linked tasks. This check box can be selected or cleared within the Schedule tab of the Options dialog box (Tools..Options). | ||||||
Automatic Leveling | The mechanism by which a project's resource assignments undergo leveling every time a change is made to the tasks/resources/assignments or manually invoked by using the Level Now button within the Resource Leveling dialog box. | ||||||
Automatic Scheduling | The mechanism by which a project's schedule (calculated with critical path analysis) is recalculated every time a change is made. The check box allows automatic scheduling to be selected or cleared within the Calculation tab of the Options dialog box. Manual scheduling can be activated by pressing the F9 key. | ||||||
Automatic Updating | Options (within the Update Project dialog box) to update work as complete through or reschedule uncompleted work to start based around the project's current date or the project's status date. | ||||||
Availability Profile | Dates when a resource is available to a project at a specific unit of availability. For example; a technical specialist may only be available from March 1 through March 31 at 50% of their available time, or three technicians are available in May, two from July to August and four from the beginning of September. Established within the resource information dialog. |
BAC | Within earned value analysis, the budget at completion value for a task is equivalent to its baseline cost. | ||||||||
Backward Pass | A calculation within critical path analysis that determines the late start and late finish dates for each task in the project, along with slack (float) values. | ||||||||
Bar (Task) | A patterned bar on a Gantt chart representing the duration and schedule of a task. | ||||||||
Bar Styles | A way to format a Gantt chart's bars to emphasize attributes including; critical tasks, milestones, summary tasks, and slack. Text can also be added to the bars. One set of styles is associated with each chart-type view. The view's parameters (including bar styles) are saved with the current project document. Set by the Format..Bar Styles command or fast-formatted using the Gantt Chart Wizard. | ||||||||
Base Calendar | A calendar that specifies shift patterns of working time and non working time for a project or set of resources. A base calendar differs from a resource calendar, which specifies working and nonworking time for an individual resource. | ||||||||
Baseline | A copy of project information prior to updating a project with progress. When a baseline is created, current schedule values are copied into their relative baseline ones:
This provides a clear comparison about the status of the project; if it is meeting its baseline or not. Created with the command: Tools..Tracking..Save Baseline. Interim baselines can also be created to assist in what-if? scenarios. | ||||||||
Baseline Bars | Bars on a Gantt chart depicting the baseline start and finish dates for tasks. | ||||||||
Baseline Cost (Task) | At the point of baseline creation, the current cost for the task (work related costs + fixed costs). | ||||||||
Baseline Duration (Task) | The task's current duration, at the point of baseline creation. | ||||||||
Baseline Start (Task) | The scheduled start of tasks at the point of baseline creation. | ||||||||
Baseline Finish (Task) | The scheduled finish of tasks at the point of baseline creation. | ||||||||
Baseline Work (Resource) | At the point of baseline creation, the total work against all assignments for a specific resource. | ||||||||
Baseline Work (Task) | At the point of baseline creation, the current work for the task. | ||||||||
BCWP | Within earned value analysis, the Budgeted Cost of Work Performed (also called earned value). A measure of the cost of work performed up to the status date or the current date. It indicates how much of the budget should have been spent, in view of the amount of work done so far, and the baseline cost for the tasks and assignments that have been progressed. Microsoft Project calculates it as the task's baseline cost multiplied by percent complete. It can be compared to ACWP to determine CV (cost variance) values and to BCWS to determine SV (schedule variance values). | ||||||||
BCWS | Within earned value analysis, the Budgeted Cost of Work Scheduled. How much needs to be spent to complete all the tasks in the project. Equivalent to the project's baseline cost. | ||||||||
Bottom-Up Planning | A method for creating a project's outline by first considering the tasks and milestones that are required prior to defining the phases that will summarize the detail. See also . | ||||||||
Box Styles | Formatting options within the network diagram to show specific task fields. These styles can be customized and applied against different task attributes: critical, non-critical, summary tasks, milestones and so on. | ||||||||
Build Team From Enterprise | The Build Team From Enterprise dialog box provides a convenient way to create a resource pool for a project from resources within the enterprise resource pool. Placeholder resources within the local pool can be replaced by real people within the enterprise pool. When building the team, filters can be applied to select suitable resources, for example possessing a suitable skill, or being at a particular level of the Resource Breakdown Structure. |
Calculated Field | A custom field in which the contents display values relative to a formula or equation. These formulae can be copied in from other project files or from GLOBAL.MPT. Calculated fields can be used to:
Enterprise fields can also contain calculated values. | ||||||||||||||||
Calendar | A definition of working time and non working time (in shift patterns) that can be applied to individual resources working on the project, or to the project and the tasks within it. The default calendar is called a base calendar. Calendars are edited or created within the Change Working Time dialog box (Tools..Change Working Time). The Organizer allows this component to be shared between projects. | ||||||||||||||||
Calendar View | Project tasks are displayed in a workplanner format, with task bars spanning the days or weeks on which the tasks are scheduled. Tasks can also be created and edited here with care. | ||||||||||||||||
Cause-And-Effect Diagram | A brainstorming technique where project risks are analyzed by the project team. Each risk is considered, along with the actions or outcomes that would cause the risk to manifest. | ||||||||||||||||
Can Level | Applying to resources, a switch (Yes/No) to allow the chosen resource to be a part of the leveling process. | ||||||||||||||||
Cell | An intersection of a row and a column within a table, a cell contains a field about a specific object (task, resource or assignment). | ||||||||||||||||
Cell Drag and Drop | A mechanism to move (dependant upon its check box being selected or cleared within the Edit tab of the Options dialog box) either:
| ||||||||||||||||
Change Controls | Changes (often from the sponsor) that affect the project. Usually impacting the project's objectives, they can be compared to the agreed client requirements definition / project requirements definition to decide upon their inclusion or exclusion, together with the impact that they will have. May require a revision to the project's baseline. | ||||||||||||||||
Chart | A type of view containing a table to the left and a timescale to the right. Delineated by a divider bar. Types of chart include:
| ||||||||||||||||
Circular Relationship | A network path that passes through the same node (task) twice; for example if task (C) is the successor to task (B), but C is also a predecessor to task (A), which is in turn a predecessor to task (B). Will cause an error in critical path analysis. | ||||||||||||||||
Client Requirements Definition | What the client / sponsor wants from the project and often a contractual obligation. Usually contains the following headings:
| ||||||||||||||||
Code | A free-format field providing additional information about the resource such as cost centre or job title. This field can be grouped and filtered upon. For more sophistication, use an outline code. | ||||||||||||||||
Collapsing | In a project's outline, a mechanism to hide normal tasks beneath their summary tasks, to see just relevant levels of detail. Usually achieved using the Hide Subtasks button. Can also be used to collapse by group and to collapse assignment detail (on task usage and resource usage views). See also expanding. | ||||||||||||||||
Column | As a part of a table, columns show field information for each task / resource / assignment in relevant cells. | ||||||||||||||||
Column Heading | The grey area to the top of each column. Clicking on a column heading selects the entire column, highlighting its field for each task or resource. Double-clicking on the column heading allows a change of field or a different title for the column. | ||||||||||||||||
Combination View | A view that contains two views. The view in the lower pane shows detailed information about the tasks or resources selected within the upper pane. The 'Task Entry' view (for example) shows a Gantt chart view in the upper pane and the task form view in the lower pane. When a task is selected in the Gantt chart, the task form view displays detailed information about that task shown above. The resource allocation view is another useful combination view. | ||||||||||||||||
Common Resource Pool | A common resource pool contains resources; people or material resources that are to be shared between a program of multiple projects. They can take two basic forms:
Within Microsoft Project 2002, consider the creation of an enterprise resource pool, especially when using Project Server. | ||||||||||||||||
Complete Through | This field indicates the progress of a task on a Gantt chart. It is the date/time that actuals have been reported up until. It is only available as a bar style. | ||||||||||||||||
Component | Components are the building blocks of a project document. In addition to the tasks, resources and assignments, components are used to manage the project's data. They include:
The Organizer can be used to manage components within the project document and between project documents. | ||||||||||||||||
Composite Project | A program file that contains one or more inserted subprojects without links to their source projects. When the composite is saved to disk, changes to the inserted projects are not reflected in their source files. | ||||||||||||||||
Consolidated Project | A program file that contains links to one or more subproject files. The inserted projects retain links to their source projects so that any changes to them within the consolidated file are passed on to the source file when the consolidation is saved to disk. | ||||||||||||||||
Contoured Assignment | An assignment where the hours are scheduled at a non-uniform rate. Microsoft Project's options include:
All contoured assignments will take more time than a flat assignment (which is the default). Contours are displayed as timephased fields within the task usage and resource usage views. | ||||||||||||||||
Constraints | A scheduling protocol that establishes when a Task should happen. Constraints (which can be flexible or inflexible) are:
See also: deadlines. | ||||||||||||||||
Cost | The total scheduled cost for a summary task, normal task, resource, or assignment or for an entire project. This is sometimes referred to as the current cost, or budget. Cost can be simply a fixed cost for a task, or it can also include costs incurred as a result of measurable work. | ||||||||||||||||
Cost / Use | A field that shows the cost that accrues each time a resource is used, irrespective of the work for the resource carrying out an assignment. | ||||||||||||||||
Cost Breakdown Structure | Used as an alternative to the WBS, the CBS is a useful way to use outline codes to group the project's tasks by cost centre. Sophisticated totals and subtotals can be created to determine how effectively the project is progressing, cost area by cost area. | ||||||||||||||||
Cost Objective | One of the three project objectives. A definition of the budget available (as defined within the client requirements and project requirements documents) in cost terms to complete a project and hopefully produce all the deliverables within the project's overall scope. This often becomes the project's baseline cost or BCWS and can be compared to actual costs to determine cost variances. See also time objective; quality objective. | ||||||||||||||||
Cost Rate Table | Defined within the resource information dialog box, resources can have a variable standard rate for the work that they will perform. Up to five rate tables can be applied, each of which can be varied over time. | ||||||||||||||||
Cost Variance | The difference between the baseline cost and total cost for a task, resource or assignment. If a task is in progress, its total cost is actual cost plus its remaining costs. See also CV. | ||||||||||||||||
Count | Specifies the incrementation of the major scale or the minor scale for the timescale of a chart. For example, if the unit is weeks, a count of 2 will show 1 increment (column) for every other week. | ||||||||||||||||
CPI | Within earned value analysis, the Cost Performance Index. Calculated as the ratio of budgeted cost of work performed (BCWP) and actual cost of work performed (ACWP). CPI = BCWP/ACWP. If this value is 1 then the project, summary task or task is exactly on budget. If the value is less than 1, then things are over budget; greater than 1, things are ahead of budget. See also CV. | ||||||||||||||||
Critical Path | The series of tasks that must be completed on time for a project to finish on schedule. Each task on the critical path is a critical task; any delay to it would delay the project's schedule. | ||||||||||||||||
Critical Path Analysis | A method for scheduling when tasks will happen. Comprising of a forward pass and a backward pass, it determines how quickly and how slowly the tasks can be accomplished. | ||||||||||||||||
Critical Task | A task that must be completed on schedule for the project to finish on time. If a critical task is delayed, the project finish date might also be delayed. A series of critical tasks makes up a project's critical path. | ||||||||||||||||
Cross-Project Links | Links between tasks in different projects. Usually created within a consolidated project, cross-project links make a task within one project dependant upon an external task in another project. | ||||||||||||||||
Crosstab Reports | Printed information about tasks and resources over a specified time period. For example, a report comprising of tasks (or resources) and assignments within the rows and periodic cost or work values in the columns. Provides similar information to a crosstab view, but with more formatting options but no data editing options. | ||||||||||||||||
Crosstab Views | Screen-based information about tasks and resources over a specified time period. Can be seen from a task's (task usage view) or from a resource's (resource usage view) perspective. Can show work and cost values and provides editing facilities. Similar to a crosstab report. | ||||||||||||||||
CTRL+Click | Holding down the CTRL (Control) key on the keyboard and clicking the left mouse button. This can be used to select more than one object when the objects are not adjacent to one another. Useful when linking tasks together with the Link Task button or removing links with the Unlink Tasks button. Can also be used in conjunction with the Task Information button to make changes to multiple tasks / resources / assignments. See also SHIFT+Click. | ||||||||||||||||
CTRL+DELETE | Removes the selected information within the current cell. Does not delete the entire object (task / resource) as the DELETE key can. | ||||||||||||||||
Current Date | The Current Date is the boundary between the past and the future. Using the PC's system date by default, it can be edited within the Project Information dialog box. Tasks between the project start date and the current date should be complete, those happening after the current date should possess remaining work. The current date display on a Gantt chart can be altered using the Gridlines dialog box (Format..Gridlines). The current date is sometimes referred to as the as-of date. See also: status date. | ||||||||||||||||
Custom Field | A field (for Tasks or Resources) that is user-definable. Entries can be made against: cost; date; duration; finish; flag; number; outline code; start; text. Custom fields can be simply renamed or can contain value lists. A calculated field can contain a formulaic expression and also display graphical indicators. Custom fields can be defined within the Customized Fields dialog box (Tools..Customize..Fields). Custom fields are project-specific and can be copied from project to project using the Organizer. See also Enterprise Fields. | ||||||||||||||||
CV | Within earned value analysis, the CV (earned value cost variance) field is calculated as BCWP - ACWP. It is the difference between how much it should have cost to achieve the current level of completion on the task and how much it has actually cost to up to the status date or the current date. A positive CV value indicates that progress against the task, summary task, project or resource is ahead of the baseline cost (under budget) and a negative value indicates that progress is currently over budget. See also CPI and cost variance. |
Dangle | A task that either has no predecessor task or no successor task linked to it. Also known as a hanger. | ||||||||||
Deadline | A date by which a task should ideally be complete by. This can affect the slack value for the task, but it does not impose any constraint upon the task. If a task exceeds its deadline it can create a scheduling conflict. | ||||||||||
Default Rate | New resources can inherit a rate; standard rate for standard work and overtime rate for overtime work. This setting, within the General tab of the Options dialog box, will only apply to newly created resources in the resource pool. | ||||||||||
Default End Time | Specifies the finish time that Microsoft Project assigns by default to tasks with a constrained finish. Usually equivalent to the end of the shift pattern for the base calendar. Defined within the Calendar tab of the Options dialog box. | ||||||||||
Default Start Time | Specifies the start time that Microsoft Project assigns by default to tasks with a constrained start. Usually equivalent to the start of the shift pattern for the base calendar. Defined within the Calendar tab of the Options dialog box. | ||||||||||
Delegation | When using Project Web Access with Project Server, team members can delegate their assignments to other team members. When this happens, the delegatee completes the work on that assignment. The delegator can then review and approve status and actuals on the assignment before returning updated information to the project manager to in turn update the project plan. | ||||||||||
Deliverables | The major things that the project (or even the tasks within it) creates to meet the overall Time / Cost / Quality objectives. These are usually listed within the client requirements definition (CRD) and project requirements definition (PRD). Deliverables may also make up the upper levels of a project's product breakdown structure (PBS). | ||||||||||
Demand Assignment | An assignment for a resource that could not be substituted by the Resource Substitution Wizard. Even if this resource has a resource conflict, the wizard can not create the substitution. See also request assignment. | ||||||||||
Dependency Types | Microsoft Project supports four types of dependencies to link one task to another:
| ||||||||||
Dependant Project | A project (or commonly a task or milestone within a project) that has its schedule driven by a task or milestone within another project. These projects often form a consolidation, with external tasks used to provide the links. | ||||||||||
Destination Program | The program into which data is placed when exchanging data from Microsoft Project. See also source program. | ||||||||||
Details | Different sets of options to display sets of information within views. Primarily used in the task form; task usage; resource usage; resource graph views. | ||||||||||
Dimmed | Options within Microsoft Project that are unavailable. This often occurs if the object is read-only or because the option is not available for the current view. | ||||||||||
Divider Bar | The vertical divider bar separates the table and chart portions of the view. The horizontal divider bar delineates a combination view with an upper pane and a lower pane. | ||||||||||
Divider Cursor | The cursor that changes the width of a column or the width of a part of the view, or the depth of a upper pane or lower pane of a combination view. Double-clicking on the cursor will force a best-fit of a chart to a table or to open or close a lower pane. | ||||||||||
Drawing | A graphical image which can be embedded as an object in Gantt charts, task notes, report headers and so on. | ||||||||||
Driver Project | A project (or commonly a task or milestone within a project) that determines the schedule of a task or milestone within another project. These projects often form a consolidation, with external tasks used to provide the links. | ||||||||||
Drop Down | An icon indicating the existence of a list. | ||||||||||
Duration | The total span of working time or elapsed time required to complete a task. When applied to summary tasks, it represents the amount of time between the start of the earliest subtask and the completion on the latest subtask. Duration can also be displayed at project level against a project summary task. Durations against tasks can be estimated or confirmed. If the task has assignments against it, the task's duration may be calculated according to the scheduling formula. | ||||||||||
Duration Suffix | A suffix after the duration value to determine the time unit the duration applies to:
Note that the number of hours per day, hours per week and days per month values are set within the Calendar tab of the Options dialog box (Tools..Options). |
EAC | Within earned value analysis, the estimate at completion shows the total scheduled or projected cost for a task, resource, or assignment. This is calculated as: EAC = ACWP + (BAC-BCWP)/CPI |
Earned Value | A measure of the cost of work performed up to the status date or the current date. It uses baseline cost values and actual work to date to show if the actual costs incurred are on budget. It indicates how much of the baseline cost should have been spent, relative to the amount of work done so far. Earned Value is also referred to as budgeted cost of work performed (BCWP). |
Earned Value Analysis | A method for determining project performance. It compares the value of the work that was planned (BCWS) with the how much work was actually earned (BCWP), with what was actually spent (ACWP). These comparisons provide invaluable information about actual conditions within the project and trends that may be developing in terms of schedule and cost performance. Earned Value Analysis is commonly abbreviated as EVA. |
Early Finish | The earliest date that a task could possibly finish, based upon dates from its predecessors or successors, other constraints, any leveling delay and the duration of the task itself. |
Early Start | The earliest date that a task could possibly start, based upon dates from its predecessors or successors, other constraints and any leveling delay. |
Effort-Driven | Where the work on a task is shared between its assignments. When resources are assigned or removed from a task, Microsoft Project will extend or shorten the duration of the task to accommodate the additional or fewer resources applied, but it will not change the total work for the task. This is the default option for new tasks. |
Elapsed Time | Time that does not take any calendar considerations into account; 24 hours a day, 365 days a year. |
Enterprise Field | A field defined within the enterprise global template. The most commonly used enterprise fields will contain enterprise outline codes or RBS values. Enterprise fields can only be created by a user with appropriate access privileges. All projects that link to the enterprise global template can use these standardized fields and apply them to tasks / resources or even projects. Enterprise field definitions can not be changed in a local project file. See also custom fields. |
Enterprise Global Template | Standard program components (including views, tables and enterprise fields) can be stored within the enterprise global template to ensure that all projects within an organization adhere to standards. Unlike GLOBAL.MPT the enterprise global template is opened from within Project Server. Only a user with administrative privileges to project server can check out and change the enterprise global template. The enterprise global template should not contain any tasks or resources. |
Enterprise Outline Code | Custom tags for common tasks, projects, or resources. Tasks can use these codes to define cost areas. Resources can use these codes for skill definition and to create assignments automatically using the resource substitution wizard. Only a user with administrative privileges can add or edit enterprise outline codes. |
Enterprise Resource Pool | A global pool of resources that are available to work upon all projects within a program. When local resources are imported into the enterprise pool by using the resource import wizard they then become enterprise resources. |
Enterprise Resources | Enterprise resources are resources that can be made available to a program of projects. They are stored within the enterprise resource pool and must be checked out of the enterprise pool (by a user with appropriate permissions) for editing of standard rates, skill codes and so on. |
Enlargement Factor | A percentage value representing the width of a minor scale increment for a chart. See also size. |
Entry Bar | Placed below the toolbars or within dialog boxes, the entry bar displays the current cell's contents. The ENTER and ESCAPE keys confirm or reject an entry and the F2 key provides in-cell editing. |
Entry Table (Resources) | Displays basic information regarding resources, including resource group, resource units, standard rate, overtime rate, cost per resource use, accrual method, and resource code. This table is mainly used in adding resources to the project's resource pool. It is the default table within the Resource Sheet view. |
Entry Table (Tasks) | Displays basic information in fields regarding tasks: ID; indicators; task name; duration; start; finish; resource names; predecessors. Mainly used to add and edit general task information. Provided by default in the Gantt chart view. |
Estimated Duration | A duration for a task suffixed with a '?' to indicate that the duration is still tentative. Tasks with estimated durations can be filtered against and reported upon. They can then be confirmed by a project manager or by workgroup members. |
Expanding | In a project's outline, a mechanism to show normal tasks beneath their summary tasks, to see more levels of detail. Usually achieved using the Show Subtasks button. Can also be used to expand by group and to show assignment detail (on task usage and resource usage views). See also collapsing. |
External Task | A task in another project (or part of the program) that is linked to a task in the current project. This can help determine the schedule of the current project (relative to linked projects). A link between a task and an external task can be edited, but an external task itself can only be edited within its own project. |
Field | Information about a project's tasks, resources or assignments. Fields (which may be contain entered values or be customized) include:
| ||||||||
File Format | Files in Microsoft Project can be saved to disk in a number of formats: .MPP (the default); .MPX (a comma delimited file - Microsoft Project 98 only); .XLS (Excel spreadsheet); .MDB (Access database). Some files (usually databases) can contain all project data. Others are normally used to export/import data using maps. A portfolio of projects can also be saved to Project Server. | ||||||||
File Properties | Details about a file that help identify it (such as a descriptive title, the author's name, the subject, and keywords that identify topics or other important information in the file). Properties can also be added to views and reports within the page setup dialog box. | ||||||||
Fill Handle | Allowing adjacent cells to be populated with the initial cell's data. Available in task usage and resource usage views and also for cells within tables. | ||||||||
Filter | Provides a way of selecting information meeting a filter criteria. Types of filter are:
| ||||||||
Filter Criteria | The statement that specifies which tasks or resources should be displayed when the filter is applied. For example, the 'Top Level Tasks' filter has the criteria: outline level >= 1. | ||||||||
Filter Library | A list of all available filters, applicable to tasks or resources. Accessed by using the Project..Filtered for..More Filters command. Originally held in GLOBAL.MPT, filters are stored to the local project document once they have been accessed. Existing filters can be edited or new ones can be created within the library. In addition, saved AutoFilter criteria are saved within the filter library as new global filters. | ||||||||
Finish (Task) | The scheduled finish for a task. | ||||||||
Finish Variance | How much a task has been delayed within a project's schedule. Calculated as the difference between baseline finish and the current scheduled finish. Often referred to as slippage. | ||||||||
Fiscal Year | With a Fiscal Year commencing other than January, Microsoft Project displays years on the timescale using the fiscal year rather than the calendar year. For example, with April as the beginning of a fiscal year, Microsoft Project displays the year "2003" for the date March 2nd, 2004. | ||||||||
Fixed Consumption Rate | Upon completion of an assignment, a fixed quantity of a material resource that will have been consumed. See also variable consumption rate. | ||||||||
Fixed Cost | A set cost against a task that remains constant regardless of the task duration or the work performed by a resource; for example a delivery of some goods, or some work that has been subcontracted to a third party organization. | ||||||||
Fixed Cost Accrual | The accrual method to schedule how fixed costs will be incurred. | ||||||||
Fixed Duration | For a constant task duration, as assigned work is increased so will assigned units. Decrease the units and the work will correspondingly reduce.
If assigned units are greater than max units, a resource conflict will arise. | ||||||||
Fixed Units | As the task's assigned units remain constant, an increase / decrease in assigned work will result in a corresponding increase / decrease in task duration. Changes to the task's duration will have a corresponding effect upon work.
Fixed Units is the default task type for new tasks. | ||||||||
Fixed Work | If assigned work should remain constant, then as a task's duration goes up assigned units will go down (and vice versa).
If assigned units are greater than max units, a resource conflict will arise. | ||||||||
Flat Assignment | An assignment where the hours are at a uniform level, unlike a contoured assignment where the hours assigned per day/week vary. | ||||||||
Flexible Constraint | As opposed to inflexible constraints, flexible ones schedule tasks as follows:
These constraints will not cause schedule conflicts if a task is delayed beyond its constrained date. | ||||||||
Float | The amount of time a task can slip before it affects another task's dates or the project finish date. Also referred to as slack. | ||||||||
FNET | Finishes the task on or after the date entered. Use this flexible constraint when a task can not finish before a specific date. | ||||||||
FNLT | Finishes the task on or before the date entered. Use this inflexible constraint when a task must finish by a specific date. Can create a scheduling conflict if this date is violated. | ||||||||
Folder | Project documents (files) are stored in folders on a local PC or on a network. Folders branch off from the root directory (usually C:\). The 'My Documents' folder is the default working folder in Windows 98/2000/XP. | ||||||||
Font | A typeface depicting letters, numbers and symbols. Font sizes and attributes can be set from the formatting toolbar, or by applying text styles or in report headers or footers by using the page setup command. | ||||||||
Forward Pass | A calculation within critical path analysis that determines the early start and early finish dates for each task in the project, along with the project finish date. | ||||||||
Footer | Text that appears at the bottom of a printed page. A footer typically contains information such as page number, total page count (for collation purposes) and date. It could also contain the project manager's name and the project's version number. | ||||||||
Form | Representing information in a format similar to a paper form. Forms show information about only one task or resource at a time. Common forms are the task form and resource form. The Organizer allows this component to be shared between projects. | ||||||||
Formatting Toolbar | Provides tools for changing how a view is displayed: fonts; text alignment; filters; outline options and so on. | ||||||||
Free Slack | Free slack (or free float) is the amount of time a task can slip before it delays any other task. See also total slack. |
Gantt Chart | A graphical representation of the project's current schedule. It will often contain bars for:
Gantt charts are also referred to as Bar Charts as they depict task bars against a timescale. | ||||||||||
Gantt Chart Wizard | A series of interactive dialog boxes containing options to quickly format a Gantt chart, it configures bar styles and layout options. Running it reconfigures any manually applied bar styles, so be careful in its use. Invoked by the Format..Gantt Chart Wizard command. | ||||||||||
Generic Resource | A placeholder resource that is a skill category that could be required to complete a task, rather than a named person. Assignments for these resources can then be replaced by real people. The resource substitution wizard can be used to substitute a generic resource with a named person. | ||||||||||
GLOBAL.MPT | A Template file (GLOBAL.MPT) that contains information applied to many projects. Information in a global file can include components such as views, calendars, forms, reports, tables, filters, toolbars, menu bars and macros. When a new project is created, it takes its components from the global file. Information within the global file can be read or written using the Organizer. Warning: Overwriting a global file may require a re-installation of Microsoft Project to reapply default settings. | ||||||||||
Global Filter | Compared to the AutoFilter (which makes selections based on column contents), the global filter shows only the tasks / resources / assignments that meet a specific filter criteria. If a filter criteria is used to emphasize, rather than select, a highlight filter can be applied instead. Global filters are one of the project's components. They reside within a filter library. | ||||||||||
Graphical Indicators | By using pictures to replace values, Microsoft Project can highlight good or poor schedule / cost performances. Usually used in conjunction with calculated fields. Views can be filtered or grouped by graphical indicator. | ||||||||||
Granularity | The degree of resolution to be applied by time unit (daily or weekly for example). Useful when leveling resources. | ||||||||||
Gridlines | To help the readability of a view, gridlines of different patterns and colours can be applied. These gridlines may appear once (such as the current date) or repeatedly (such as the lines that divide rows and columns). | ||||||||||
Group | The ability to sort and subtotal a view by applying group criteria. Pre-defined groups include: 'milestones' and 'constraint types' for tasks and 'resource group' and 'Response Pending' for resources. Custom groups can be created and applied by using the Project..Group By... command and they can be shared between projects by using the Organizer. | ||||||||||
Group Criteria | Similar to filter criteria, group criteria determine the fields (for tasks or resources) that the grouping sorts upon. There can be groups within groups. Sophisticated grouping can be achieved with the use of outline codes. | ||||||||||
Group Library | A list of all available groups, applicable to tasks or resources. Accessed using the Project..Group by:..More Groups command. Originally held in GLOBAL.MPT, group criteria are stored to the local project document once they have been accessed. Existing group criteria can be edited or new ones can be created within the library. |
Hanger | A task that either has no predecessor task or no successor task linked to it. Also known as a dangle. |
Header | Text that appears at the top of a printed page. A header typically contains information such as the project or company name, together with the project start and project finish dates. |
Highlight Filter | Instead of selecting the tasks / resources that meet the filter criteria (as with a global filter), a highlight filter is used for emphasis. |
Highlights | A highlight will emphasize specific tasks or resources whilst still displaying all tasks or resources. To set the text style for highlighted information, use the Format..Text Styles command. |
Hours Per Day | The constant value that Microsoft Project uses when calculating duration and work. Taking the default of 8 hours, a one-day task will be calculated as 8 hours and an assignment of 1 unit will calculate as 8 hours also. Changing the hours per day to 6 would retain the assigned work as 8 hours and change the duration of the assignment to be 1.33 days. If the shift pattern for that day is unaltered (from the default 8 hours), the assignment (and task) will be complete at the end of that day and not within the next day. |
Hours Per Week | The constant value that Microsoft Project uses when calculating duration and work. Taking the default of 40 hours, a one-week task will be calculated as 40 hours and an assignment of 1 unit will calculate as 40 hours also. Changing the hours per week to 32 would retain the assigned work as 40 hours and therefore change the duration of the assignment to be 1.25 weeks. If the shift pattern for that week is unaltered (from the default 8 hours/day), the assignment (and task) will be complete at the end of that week and not within the next week. |
HTML | Hypertext Markup Language. Web pages are written in HTML. They often end with an .htm or .html extension. Microsoft Project's help files are HTML compliant, allowing the creation of user-defined help. Custom Project Guides can also be written using HTML. |
HTML Template | A template of HTML tags and codes that are exported along with project data. |
Hyperlink | From your project file, hyperlinks can be created to jump to other files (using a URL) on a local computer, network or intranet, or to the World Wide Web itself. This destination file can be another Microsoft Project file, other Microsoft Office documents, or any web site. |
ID | Displays the identifier number that Microsoft Project automatically assigns to each task or resource as it is added to the project. Entries in lower rows within a table will have higher ID values. The ID is usually displayed in a row heading (the grey area to the left of each row). This ID may change as a result of a cell drag and drop. See also unique ID. | ||||||||||||
Indenting | Moving a task to a lower outline level (to the right) in the task name column. When a task is indented, it becomes a subtask of the summary task above it. See also outdenting. | ||||||||||||
Indicators | Small icons representing information for a task or resource that are displayed in the indicators column within a table. Pointing to an indicator reveals additional information associated with it. Indicators include:
| ||||||||||||
Inflexible Constraint | As opposed to flexible constraints, inflexible constraints schedule tasks as follows:
If a task is delayed beyond its constrained date, an inflexible constraint can cause a scheduling conflict. | ||||||||||||
Information Dialog Boxes | Invoked by the Resource Information button, dialog boxes that allow immediate changes to tasks, resources and assignments. Can be used to change default settings or to update with revised estimates, schedule revisions, achieved progress and so on. | ||||||||||||
Initial Assignment | The first assignment of a resource (or resources) to a task. This assignment determines the total work for the task. If any assigned units are subsequently altered, the task's duration may have to change to balance the scheduling formula. Changes to an assignment should be performed within a task form view, as it displays all data relevant to that assignment. | ||||||||||||
Inserted Project | A project file embedded within a consolidated project. Changes made within the consolidation will be saved within the inserted project's file. | ||||||||||||
Interim Baseline | In addition to a master baseline, a further 10 baselines can be set. These can used in what-if? scenarios and as useful schedule comparisons. As an addition, current start and finish dates for all tasks or just those selected can be copied to interim values (Start1/Finish1). Both of these options can be accessed within the Save Baseline dialog box (Tools..Tracking..Save Baseline). Interim baseline information can be displayed on charts using a variety of bar styles. |
Lag | A delay on the link between a predecessor and a successor; for example to create a 5 day delay between finishing one task and starting another. Lag times can also be a percentage of the duration of the predecessor task. A negative value against a lag is known as a lead. | ||||||||||||||
Labels | Standard formatting option to express a chart's timescale. For example: 'Feb/02/04' or '02/02/04'. | ||||||||||||||
Landscape | A horizontal page orientation, with more columns than rows, this style is best suited to charts and crosstab reports. | ||||||||||||||
Layout | A formatting option that defines the general appearance of a chart, the positioning of task bars or boxes and the displaying of links to improve screen-based or printed views. | ||||||||||||||
Late Finish | A task's late finish is the latest date that a task can finish without delaying the project finish date. This date is based on the task's late start date and duration, as well as the late start and late finish dates of predecessor and successor tasks, together with any other applied constraints. | ||||||||||||||
Late Start | A task's late start is the latest date that a task can start without delaying the project finish date. This date is based on the task's scheduled start date, as well as the late start and late finish dates of predecessor and successor tasks, together with any other applied constraints. | ||||||||||||||
Lead | An overlap between a predecessor and a successor. For example, if a task can start when its predecessor is half finished, use a finish-to-start dependency with a lead time of 50 percent. Lead time is entered as a negative lag value. | ||||||||||||||
Left-Aligned | Text aligned to the left-hand side of a column or cell. | ||||||||||||||
Legend | General project information displayed at the base of a printed page, together with the explanatory list of symbols printed on a chart. Note that this display is shown or hidden within the Page Setup dialog box, but its contents are controlled by the currently chosen bar styles. | ||||||||||||||
Level Now | A command within the Resource Leveling dialog box to commence the leveling process. Also copies a task's scheduled start and scheduled finish values into relative preleveled values. | ||||||||||||||
Leveling | Resolving resource conflicts or overallocations by delaying or splitting certain tasks. During leveling, assignments are rescheduled according to the resource availability profiles, assigned units, and resource calendars, as well as the task's duration and constraints. Leveling can be controlled by various leveling parameters. It is instigated either automatically or (more commonly) by the command level now. | ||||||||||||||
Leveling Delay | Leveling Delay is how much a task (or assignment) has been delayed to resolve any resource conflicts. It is often drawn on a Gantt chart from a task's early start to its scheduled start. Leveling delays can be entered manually of created as a result of resource leveling. Clearing leveling will clear any previously applied leveling delays. | ||||||||||||||
Leveling Gantt View | A variation of the Gantt chart view, showing what has happened as a result of the leveling process. The Table portion displays a list of tasks and information about leveling delays. The chart portion shows a comparison of the bar's current schedule with its preleveled state, together with an indication of the leveling delay that has been applied. | ||||||||||||||
Leveling Order | Parameters that establish how tasks are leveled around other tasks. Three options are available:
| ||||||||||||||
Leveling Parameters | Switches that determine how leveling is performed. They include:
See also selective leveling. | ||||||||||||||
Lifecycle | The period of time between the project moving from a simple collection of ideas in a client requirements definition to a finished entity that meets all its originally agreed requirements. Often defined within a methodology, it can be summarized into four basic headings:
As the majority of measurable work is contained within the 'Do' stage, this is where the majority of the project's costs will come from and where the majority of the project's risks will be found. | ||||||||||||||
Link | Links between tasks represent the sequence in which they will occur. For example; the successor task 'Boil Water' will first depend upon the completion of the predecessor task 'Fill Kettle'. Links can have a number of dependency types. Create links by selecting two tasks (with click and CTRL+Click), followed by the Link Tasks button. | ||||||||||||||
Local Defaults | As compared to default settings that apply to Microsoft Project in general (which are saved within the PC's registry), local defaults apply to the current project only and override any inherited settings. These settings usually apply to the view, schedule and calculation parameters of the project. | ||||||||||||||
Local Resource | Local resources are resources local to a specific project and not part of an enterprise resource pool. | ||||||||||||||
Lower Pane | As part of a combination view, the object (task / resource) in the upper pane selects the detailed information that is displayed in the lower pane beneath. For example, with a Gantt chart view in the upper pane and the task form view in the lower, when a task in the Gantt chart is selected, the task form view displays detailed information about just the selected task. |
Major Scale | Specifies the units and count for the upper lines (tiers) of the timescale of a chart. Its units must be larger than or equal to the minor scale units. |
Manual Scheduling | When Microsoft Project calculates the schedule of the project at a user's request (rather than automatic scheduling - the default). This can apply to all open projects or just the currently active project. Manual scheduling can be activated by pressing the F9 key. |
Map | A customizable set of instructions to export task, resource, and assignment data to other applications such as Access or Excel. Maps can be based on existing tables and can have filters applied to them. Maps can also be used to import data back into a project file (with care). The Organizer allows this component to be shared between projects. |
MAPI | The acronym for Messaging Application Programming Interface, which is the standard Microsoft email programming interface. |
Margins | The distance (in centimeters or inches) between the top, bottom, right and left of the page to the area that will be printed upon. |
Mask | Applied to outline codes and WBS codes, the mask defines the numeric and alphanumeric strings that make up the code, together with the delimiters that separate them. |
Master Project | A project containing one or more subprojects. The subprojects can be inserted into a master composite project or they can be embedded within a master consolidated project. These subprojects often share resources by accessing a common resource pool. |
Material Resources | Consumables that are assigned to tasks in a similar way to normal work-type resources. Material resources are consumed by the tasks to which they are assigned (and hence incurring cost), but they do not create any measurable work. |
Matrix Organization | An organizational structure in which the project manager shares responsibility with functional managers for assessing priorities and assigning tasks to resources that may or may not be within their own workgroup. |
Max Units | Contains the maximum percentage or number of units of resource availability, the default value being 100 percent. It can be varied with an availability profile. Resource conflicts can arise if assigned units > max units (which can happen with task types that are not fixed units). |
Menu Bar | The menu bar is used to select menus and commands to perform actions within Microsoft Project. It appears below the program's title bar and it can be customized. |
Methodology | A statement of how the project will be managed, including its lifecycle, terms of reference, reports required and so on. Methodologies can be informal or company specific. PRINCE is an example of a commercially available project management methodology. |
MFO | Finishes the task on a specific date. Use this inflexible constraint when a task has to finish on a given date. Can create a scheduling conflict if this date is violated. |
Milestone Tasks | A reference point marking a major event in a project and used to monitor the project's progress. Milestones are usually tasks with a duration of 0 time units (hours, days or even weeks) and may often have a constraint applied to them or they may be an external task within a consolidated program. |
Minor Scale | Specifies the units and count for the lowest line (tier) of the timescale of a chart. Its units must be smaller than or equal to the major scale units. |
Module | A simple program (usually written in VBA) to automate a command or procedure. Also referred to as a macro. The Organizer allows this component to be shared between projects. |
Monte Carlo Analysis | A form of quantitative risk analysis that, using complex sequences of random numbers, creates a likely distribution of various project schedules. A much simpler method is provided by PERT analysis. |
MSO | Starts the task on a specific date. Use this inflexible constraint when a task has to start on a given date. Can create a scheduling conflict if this date is violated. |
MPP | The default binary file storage format for Microsoft Project. Can not be read by any other applications. |
Multiple Critical Paths | Microsoft Project can calculate and display a critical path for each independent network of tasks within the project or program. This sets the late finish date for tasks without successors or constraints to be to be the same as their early finish date, thus becoming critical. A project-specific setting, this setting is set or cleared within the Calculation tab of the Options dialog box (Tools..Options). |
Multiple Task Information | A variation of the Task Information dialog that allows one setting to be applied to several tasks at the same time. For example; to change two tasks to be a fixed duration type, select both of them (with Click and CTRL+Click) and then click on the Task Information button. |
My Documents Folder | The My Documents folder is the default working folder used by Microsoft Office applications. Documents will be opened from or saved to this folder by default. |
Negative Slack | When the total slack (or total float) on a task is negative, its scheduled finish is too late for its successor(s) to begin on the date required by an inflexible constraint. Negative slack is sometimes referred to as 'Hyper-Criticality'. |
Network | A combination of predecessor and successor tasks linked together in a logical sequence by means of precedence. |
Network Diagram | A diagram that graphically shows tasks and their associated links. Tasks are represented by boxes (or nodes), and links are represented by lines that connect the boxes. Various layout and box style options are available. Network Diagrams are also referred to as PERT charts. |
Non-Critical Path | The series of tasks that need not be completed on time for a project to finish on schedule. Each task on the non-critical path possesses a degree of slack. |
Non-Critical Task | A non-critical task possesses some slack (or float). This task can be delayed within its slack without delaying the project finish date. |
Non Working Time | Time scheduled by the shift pattern within a calendar to indicate when work can not be accomplished. Microsoft Project's default non working values are from 12AM-8AM, 12PM-1PM and 5PM-12AM (00:00-08:00 and 12:00-13:00 and 17:00-24:00). |
Normal Tasks | The most common task. Assignments are made against normal tasks. Drawn on a Gantt chart from scheduled start to scheduled finish. |
Objectives | Why you are doing the project, as listed in the client requirements definition. The business benefits that the project will provide when it is completed. Often broken down to three basic project objectives: Time; Cost; Quality. | ||
Office Assistant | The animated character that provides advice within Microsoft Project and other Microsoft Office products. Can also be used to locate specific help topics and items. | ||
OLE | Object Linking and Embedding - a program-integration technology to share information between applications. Information can be shared through linked and embedded objects between all application programs that support OLE. | ||
Organization Breakdown Structure | A hierarchical depiction of the project organization, often broken down by functional area, department, manager, team leader and so on. This links with the work breakdown structure to form a responsibility matrix. An OBS is often referred to as a Resource Breakdown Structure. | ||
Organizer | A tabbed dialog box in which to copy project components: views, tables, filters, calendars, reports, forms, toolbars, maps, and VBA modules to other documents. It can also copy objects to and from the GLOBAL.MPT file. | ||
Orientation | The aspect of a printed view or report. Charts suit a landscape orientation, whilst sheets suit a portrait orientation. | ||
Outdenting | Moving a task to a higher outline level (to the left) in the task name column. Usually done with the Outdent button. See also indenting. | ||
Outline Code | A user-defined code that is primarily used to identify tasks within the project. This code (which can be formatted using a mask) can be used to create additional structures within the project (for example cost breakdown structures or product breakdown structures) in addition to the standard WBS. Outline codes can also be applied to resources. Use enterprise outline codes for use in a program environment. | ||
Outline Level | The hierarchical position of the task within the project's outline. A level of 1 is at the top (usually the main summary tasks) with levels 2,3,4 and so on representing subsequent levels beneath. | ||
Outline Number | Numbers that indicate where a task is positioned in the project's outline. For example, a task with an outline number of 3.4 indicates that it's the fourth subtask within the third top-level summary task. | ||
Outline Symbol | An icon beside a summary task to indicate that its subtasks are displayed, or collapsed. Clicking on the icon will expand or collapse the outline, similar to the way that Windows Explorer expands or collapses the view of folders on a hard disk. | ||
Overtime Rate | A rate applied against a resource for work (by the hours or days or even week) which is entered as overtime work. | ||
Overtime Work | The amount of work on an assignment that can be scheduled beyond a resource's normal shift pattern. Charged at the resource's overtime rate, it is not additional work against the assignment. For example, if an assignment has 48 hours of standard work and 16 hours of overtime work, the total work on the assignment is 48 hours, but the assignment will only take 32 hours to complete, hence reducing the duration of the assignment and potentially reducing the duration of its related task. |
Page Break | A way to keep related information on a page by inserting a page break, putting the information above the break (shown by a gridline) on one page and the information below the break on another printed page. | ||
Page Setup | Providing controls for; margins, orientation, headers, footers and other general formatting options when printing views and reports. | ||
Parallel Assignments | When assignments for a resource overlap in the same time frame. This often causes a resource conflict if demand exceeds supply. | ||
Peak Units | The highest assigned units value for all assignments for a resource. If a resource is assigned to 1 task at 50% assigned units and another task at 150% assigned units, the peak units value would be 150%. If peak units > max units, there will be a resource conflict. | ||
Percent Complete | When a task is first created, its percent complete is zero. When the task is updated with values for actual duration, remaining duration, or actual work (which affects actual duration), Microsoft Project calculates percent complete as:
If a value is entered in the % Complete field, Microsoft Project automatically calculates actual duration and remaining duration, based around the a task's currently scheduled duration. Microsoft Project will also copy a task's scheduled start into actual start and scheduled finish to actual finish if the task is marked as 100% complete. | ||
Percent Work Complete (Resources) | The percentage of the resource's work that has been completed. It is a calculated value based upon the actual work done by the resource across all their assignments, using the formula: Percent Work Complete = (Actual Work / Work) * 100. | ||
Percent Work Complete (Task) | The percentage of the task's work that has been completed. Either an entered value, or it is calculated from the actual work (task) as percent work complete = (actual work / work) * 100 (by default). | ||
PERT Analysis | PERT analysis is a simple form of quantitative risk analysis and can be applied to a schedule to help estimate the duration of a task. After the entry of optimistic, pessimistic, and expected durations for each of the tasks, Microsoft Project will calculate a weighted average of the three durations and determine a single duration estimate for each task. |